§4160.11. Inspection and acceptance of work
The governing authority of any municipality or parish taking advantage
of the provisions of this Chapter shall, upon the completion of any contract
awarded as provided for herein, provide for the final inspection of the work
performed thereunder and the improvements made, and if the work be found
to have been completed satisfactorily in accordance with said contract, as
evidenced by a certificate of the project engineer, the said governing authority
shall by ordinance duly adopted approve and accept the said work and fulfill
its obligations under the said contract after compliance with the laws of
Louisiana relative to the completion of contracts involving public works, by
full payment therefor of any and all amounts and balances due the said
contractor, including all retained percentages of payments previously made
thereon on engineer's estimates, and which percentages were retained pending
the completion of the said work.
Acts 1990, No. 782, §1, eff. July 24, 1990.