§126. Change orders
The prior approval of the Joint Legislative Committee on the Budget is required for
one or more change orders that cause an excess in the aggregate of two hundred fifty
thousand dollars per month for a project undertaken pursuant to an appropriation in the
Capital Outlay Act. In addition, a change order for a project undertaken pursuant to this Part
shall also be subject to the approval of the commissioner of administration. Any change order
in excess of fifty thousand dollars but less than two hundred fifty thousand dollars shall be
submitted to the Joint Legislative Committee on the Budget for review but shall not require
committee approval.
Acts 1989, No. 836, §1, eff. July 1, 1989; Acts 1997, No. 924, §1, eff. July 1, 1997;
Acts 2008, No. 859, §1; Acts 2014, No. 748, §2, eff. June 19, 2014; Acts 2025, No. 183, §1,
eff. June 8, 2025.